Sloane Street

Sloane Street - Programme

The public realm improvement works will be delivered in three sections, beginning at the southern end of Sloane Street towards the end of 2019 and completing within three years.

The works are being phased so we can ensure that the road remains open to traffic and access is maintained to all frontages for the full duration of the works

Ahead of the main construction works, we need to carry out a series of surveys along Sloane Street to identify the location of utilities and services under the existing road and pavement. These surveys begin this summer and will take approximately six weeks to complete. They will include digging exploratory holes in the pavement but this will not affect traffic or pedestrian access.

Phase one

Southern Section: Sloane Square to Cadogan Gate

Works will begin later this year and will take up to two years to complete:

 

Phases two and three

Central Section: Cadogan Gate to Cadogan Place

Northern Section: Cadogan Place to Knightsbridge

Following completion of the southern section, works on phases two and three are expected to begin in summer 2021.

 

Last updated: 22 February 2023